Nassau County Demolition Debris: The 180-Day Permit Clock and Your Dumpster Schedule
Short answer: in unincorporated Nassau County, the County’s demolition permit application says final inspection is required within 180 days of issuance and that all debris must be removed from the site before that final inspection. If you are tearing something down, your dumpster schedule is part of your permit timeline.
This guide uses Nassau County Building Department documents checked on November 10, 2026. Rules and forms are updated often, so confirm with the department before you start.
Which office issues the permit?
The Nassau County Building Department, at 96161 Nassau Place in Yulee, handles unincorporated Nassau County and posts its forms on its Permits page, including a Demolition Permit application. Fernandina Beach, Callahan and Hilliard are separate municipalities with their own building offices, so the County form does not cover a job inside those city or town limits. Call the office for your address first.
What the County demolition application says
- Final inspections are required within 180 days of issuance.
- All debris must be removed from the site before the final inspection.
- The application asks for the demolition method (by hand or by machine) and whether utilities are still connected and electrical is energized, so plan disconnects before the crew arrives.
- The form includes asbestos notification language; ask the Building Department what applies to your structure before demolition.
You can read the form itself here: Nassau County Demolition Permit application.
Replacement homes have a related 180-day clock
The County’s impact and mobility fee exemption guide for replacement structures says that when a previously existing lawful structure remains after the replacement is built, the permit holder must apply for a demolition permit within three business days of a Temporary Certificate of Occupancy, and the old structure must be removed within 180 days of the demolition permit to avoid revocation of the Temporary Certificate and possible Code Enforcement action. If that is your situation, read the guide directly or ask the County, because the details depend on your approval.
Turning that timeline into a dumpster plan
- Work backward from the final inspection date and the 180-day limit, then leave room for rain delays.
- Separate clean heavy debris from mixed debris before you order, and tell us which you expect; concrete, rock and dirt are confirmed per order.
- Confirm where the container will sit. See our right-of-way permit checklist for Duval County for the type of questions to ask any city or county about street placement.
- If crews will be on site for weeks, ask about portable toilets at the same time.
Ready to plan? Start an online order or quote, see our roll-off dumpster options or portable toilet rentals, or contact us with the job address. Availability, sizes and dates are confirmed per address, and concrete, rock and dirt require confirmation for each order before they can be accepted.
Quick FAQ
Does a Nassau County demolition permit require debris to be cleared?
Yes. The County application states all debris must be removed from the site prior to the final inspection.
Is a Fernandina Beach teardown covered by the County permit?
Not necessarily. Fernandina Beach has its own Building Department, so contact it for jobs inside the city.
Posted on November 10, 2026 in General